Lift Planning Guide UK | Lift Plans, BS 7121 & LOLER Explained

Lift Planning Guide

How to Plan Safe Lifting Operations in Accordance with BS 7121

A lift plan is a documented plan that explains how a lifting operation will be carried out safely. It identifies the load, lifting equipment, lifting accessories, personnel involved, hazards and the sequence of the lift.

Last Reviewed: July 2026

Lift Planning Guide

How to Plan Safe Lifting Operations in Accordance with BS 7121

A lift plan explains how a lifting operation will be carried out safely. It should identify what is being lifted, the lifting equipment and accessories being used, the people involved, significant hazards, site conditions and the planned sequence of the operation.

Under the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), lifting operations involving lifting equipment must be properly planned by a competent person, appropriately supervised and carried out safely.

That does not mean every lift needs the same amount of paperwork. The level of planning should be proportionate to the complexity and risk of the operation.

BS 7121 provides recognised industry guidance for the safe use of cranes and the management of lifting operations. Together with LOLER, PUWER, manufacturer information and a suitable risk assessment, it helps lifting teams establish how an operation should be organised before the load leaves the ground.

If you are responsible for planning lifting operations professionally, our NPORS Appointed Person Lifting Operations Training develops the knowledge required to assess lifting tasks, select equipment and plan lifting operations safely.

LIFT PLANNING AT A GLANCE

What Does a Lift Plan Need to Cover?

Who Plans the Lift? A competent person with sufficient knowledge and experience for the lifting operation being planned.
Does Every Lift Need Planning? Yes. The level of planning should be proportionate to the complexity and risks involved.
What Must Be Considered? The load, equipment, accessories, capacities, ground conditions, hazards, people, communication and lifting sequence.
Which Guidance Applies? LOLER establishes legal duties, while BS 7121 provides recognised industry guidance for crane operations.

What Is Lift Planning?

Lift planning is the process of deciding how a lifting operation will be completed safely before work begins.

It goes much further than deciding whether a crane, excavator or telehandler can physically pick something up.

A properly planned lifting operation considers the complete task from start to finish. Depending on the lift, this can include:

  • The load and its confirmed weight
  • Dimensions and centre of gravity
  • Suitable lifting points
  • The lifting machine
  • Machine configuration
  • Required operating radius
  • Lifting capacity
  • Lifting accessories
  • Working Load Limits
  • Sling configuration and angles
  • Ground conditions
  • Underground and overhead services
  • Nearby structures and obstructions
  • Exclusion zones
  • Personnel involved
  • Communication arrangements
  • Weather conditions
  • The planned sequence of the lift
  • What happens if conditions change

The lifting team should understand what is going to happen before the load is raised.

Good planning removes as much uncertainty as reasonably possible and reduces the need for people to make rushed decisions while a load is suspended.

If you are unfamiliar with load ratings and lifting accessory terminology, our SWL vs WLL Explained Guide explains the difference between Safe Working Load and Working Load Limit.

Does Every Lifting Operation Need a Lift Plan?

Every lifting operation involving lifting equipment at work must be properly planned by a competent person.

However, properly planned does not mean every lift requires an identical written document or the same level of detail.

A straightforward repetitive operation involving known equipment, familiar loads and controlled conditions may require relatively simple planning.

A difficult or unusual lift involving restricted space, unusual loads, challenging ground conditions, multiple pieces of lifting equipment or significant surrounding hazards will require much more detailed consideration.

The important principle is that the planning must be suitable for the actual lifting operation and its risks.

A previous lift plan should therefore never be copied blindly simply because the lift looks similar.

If the machine, load, radius, ground conditions, lifting accessories, personnel, weather or surrounding hazards have changed, the plan may need to change too.

Basic, Intermediate and Complex Lifts

Different organisations may use their own terminology and procedures to classify lifting operations.

A useful way of understanding the principle is to consider how the complexity and risk of the operation increase.

The More Complex the Lift, the More Detailed the Planning

Basic Lift

Routine lifting in familiar conditions using suitable equipment, established procedures and competent personnel.

Intermediate Lift

An operation requiring additional consideration because of the load, restricted working space, site conditions or other hazards.

Complex Lift

An unusual or higher-risk operation requiring detailed planning, additional controls, specialist knowledge or increased supervision.

BS 7121 is a series of British Standards covering the safe use of cranes.

It is widely recognised across UK construction, civil engineering and lifting operations and provides guidance on areas including the organisation, planning, management and safe execution of crane operations.

BS 7121 is not itself legislation.

However, it provides recognised industry guidance that can be used alongside statutory duties such as LOLER and PUWER.

Lift planning in accordance with recognised industry practice can involve:

  • Competent personnel
  • Selection of suitable lifting equipment
  • Reliable load information
  • Equipment capacity
  • Lifting accessories
  • Risk assessment
  • Ground and site conditions
  • Communication
  • Supervision
  • Exclusion zones
  • Inspection and examination requirements
  • Safe systems of work
  • Procedures for dealing with changes

A lift plan should therefore be regarded as an important part of controlling the operation rather than paperwork produced simply to satisfy a site requirement.

What Does LOLER Say About Lift Planning?

LOLER requires lifting operations involving lifting equipment to be properly planned by a competent person, appropriately supervised and carried out safely.

The amount of planning and supervision required depends on the lifting operation.

For a fuller explanation of the legislation and how it applies to lifting equipment, lifting accessories, planning and thorough examination, read our LOLER Explained Guide.

Who Is Responsible for Preparing a Lift Plan?

The person planning a lifting operation must be competent for the type and complexity of operation involved.

For crane operations organised in accordance with recognised industry practice, this planning responsibility is commonly associated with the Appointed Person.

However, planning a lift is only one part of the operation.

Different members of the lifting team have different responsibilities.

LIFTING TEAM

Who Does What During a Lifting Operation?

Appointed Person Plans and organises the lifting operation and establishes how it will be carried out safely.
Lift Supervisor Supervises the lifting operation and ensures it is carried out in accordance with the agreed plan.
Slinger Signaller Slings and controls the load and communicates with the lifting equipment operator.
Operator Operates the machine safely within its capabilities, manufacturer guidance and the agreed lifting operation.

The Appointed Person’s Role in Lift Planning

The Appointed Person can have overall responsibility for planning and organising the lifting operation.

Depending on the operation, duties may include:

  • Assessing the lifting task
  • Identifying hazards
  • Selecting suitable lifting equipment
  • Determining the lifting method
  • Establishing equipment configuration
  • Considering load weight and centre of gravity
  • Selecting appropriate lifting accessories
  • Considering ground conditions
  • Establishing exclusion zones
  • Planning communication arrangements
  • Coordinating the lifting team
  • Preparing the lift plan
  • Establishing how foreseeable changes will be managed

This is a responsible role requiring genuine knowledge and understanding of lifting operations.

Vally Plant Training provides NPORS Appointed Person Lifting Operations Training for people responsible for planning and managing lifting operations.

What Does the Lift Supervisor Do?

The Lift Supervisor has a different role.

The supervisor is responsible for controlling the lifting operation on site and ensuring it is carried out in accordance with the agreed plan.

This can involve:

  • Briefing the lifting team
  • Checking that planned controls are in place
  • Monitoring the operation
  • Maintaining exclusion zones
  • Confirming the correct equipment is being used
  • Ensuring agreed communication arrangements are followed
  • Stopping the operation if conditions become unsafe

A Lift Supervisor should not simply change an established lifting method because another approach appears quicker.

If circumstances change and the original plan is no longer suitable, the operation should be stopped and the situation dealt with by the appropriate competent person.

Our Lift Supervisor Training and Crane Supervisor Course develops the knowledge required to supervise lifting operations, work from a lift plan and coordinate the lifting team safely.

What Does the Slinger Signaller Do?

The Slinger Signaller works closely with the load and lifting equipment operator.

Depending on the operation, responsibilities can include:

  • Selecting suitable lifting accessories
  • Checking accessories before use
  • Attaching the load correctly
  • Checking lifting points
  • Considering load balance
  • Controlling the load
  • Maintaining safe positioning
  • Directing the operator
  • Using agreed hand signals or radio communication
  • Monitoring the load during movement

Clear communication is particularly important where the operator cannot see the complete lifting operation.

Vally Plant Training provides NPORS Slinger Signaller Training covering practical slinging, load control, lifting accessories and communication.

What Should a Lift Plan Include?

There is no sensible one-size-fits-all lift plan because lifting operations vary enormously.

Depending on the operation, the plan may need to include:

  • Description and identification of the load
  • Confirmed load weight
  • Load dimensions
  • Centre of gravity
  • Suitable lifting points
  • Lifting equipment being used
  • Machine or crane configuration
  • Required operating radius
  • Rated capacity at that configuration
  • Lifting accessories
  • Working Load Limits
  • Sling arrangement
  • Sling angles where applicable
  • Ground conditions
  • Machine positioning
  • Underground services
  • Overhead services
  • Nearby structures and obstructions
  • Weather conditions
  • Access and egress
  • Exclusion zones
  • Personnel involved
  • Individual responsibilities
  • Communication method
  • Sequence of operations
  • Emergency arrangements
  • Foreseeable changes that could affect the lift
PRACTICAL CHECK

Before the Load Leaves the Ground

Can the lifting team clearly explain what is being lifted, what it weighs, which machine and accessories are being used, whether they have sufficient capacity, where the machine and load will travel, who is controlling the operation and what will happen if conditions change? If not, the lift is not ready to begin.

Why Is the Load Weight So Important?

A lifting plan cannot be based on guesswork.

The person planning the operation needs reliable information about the load so that suitable lifting equipment, configuration and accessories can be selected.

Load information may come from:

  • Manufacturer information
  • Engineering drawings
  • Delivery documentation
  • Markings on the load
  • Reliable technical information
  • An appropriate method of establishing the weight where necessary

The centre of gravity is equally important.

A load can rotate, tilt or become unstable if its centre of gravity and lifting points have not been properly considered.

Working Load Limit and Lifting Accessories

Selecting the lifting machine is only part of the operation.

Slings, shackles, hooks, lifting beams and other lifting accessories also need to be suitable for the load and lifting arrangement.

The lifting team needs to understand the relevant Working Load Limit (WLL) and how the way an accessory is configured can affect its capacity.

Our SWL vs WLL Explained Guide explains these terms in more detail and why Working Load Limit is so important when selecting lifting accessories.

Ground Conditions and Machine Positioning

The lifting equipment may have enough theoretical capacity for the load but still be unsafe if it is positioned on unsuitable ground.

Planning should consider factors such as:

  • Ground bearing capacity
  • Soft or recently disturbed ground
  • Trenches and excavations
  • Underground services
  • Voids
  • Basements
  • Slopes
  • Outrigger or stabiliser loads where applicable
  • Distance from excavation edges
  • Access routes

Machine positioning also affects lifting radius and therefore available lifting capacity.

A seemingly small change in machine position can alter the conditions on which the original lift plan was based.

Overhead and Underground Services

Services need to be considered before lifting begins.

Overhead electricity lines can present a serious risk to lifting equipment, loads and personnel.

Underground services may also affect where heavy lifting equipment can safely travel, position or deploy stabilisers.

These hazards should be identified during planning rather than discovered once the machine is already in position.

Communication During a Lifting Operation

Everyone involved needs to understand how instructions will be communicated.

Depending on the operation, this may involve:

  • Recognised hand signals
  • Radio communication
  • Direct verbal communication
  • A designated signaller
  • Agreed emergency stop arrangements

The operator needs to know whose instructions to follow.

Conflicting instructions from several people can quickly make a lifting operation unsafe.

Candidates responsible for attaching and controlling loads and communicating with operators can complete our NPORS Slinger Signaller Training Course.

Exclusion Zones and Suspended Loads

People who are not involved in the lifting operation should be kept away from areas where they could be exposed to danger.

The lift plan should consider where the load will travel and where personnel can safely stand.

No one should place themselves beneath a suspended load or in a position where they could be trapped or struck if the load moves unexpectedly.

The exclusion zone needs to reflect the actual lifting operation rather than simply placing a few barriers immediately around the machine.

Lift Planning When Using an Excavator as a Crane

Excavators are frequently used to lift and position suspended loads, but lifting is different from normal digging duties.

Consider an operation where a contractor needs to lower a 2.8-tonne precast concrete manhole ring into an excavation using a suitable 13-tonne excavator equipped for lifting.

Before the load is lifted, the planning may need to establish:

  • The confirmed weight of the manhole ring
  • Its centre of gravity and lifting points
  • The excavator’s lifting capacity
  • Required lifting radius
  • Machine configuration
  • Manufacturer lifting information
  • The approved lifting point on the excavator
  • Suitable lifting accessories
  • Working Load Limits
  • Ground stability
  • Distance from the excavation edge
  • Underground and overhead services
  • Machine positioning
  • Exclusion zones
  • Personnel involved
  • Communication arrangements
  • The lifting sequence

The fact that the excavator can physically pick up the load does not by itself establish that the operation is safe.

Operators using excavators for suspended loads can develop the additional knowledge required through our NPORS Excavator as a Crane Training Course.

For a broader technical explanation of the hazards involved, read our Excavator as a Crane Safety Guide.

Lift Planning When Using a Telehandler

Telehandlers can also be involved in lifting operations.

Where a telehandler is being used with an approved lifting attachment or to handle a suspended load, the plan needs to consider the machine’s configuration, attachment, load, capacity, operating radius, ground conditions and manufacturer information.

Suspended-load operations introduce different hazards from conventional fork-mounted load handling.

The fact that an operator already holds a normal telehandler category should not automatically be taken to mean that every suspended-load lifting operation is covered.

Where appropriate, additional training and assessment may be required for the work being undertaken.

Common Lift Planning Mistakes

Even experienced lifting teams can get into difficulty when assumptions replace proper planning.

Common problems include:

  • Guessing the weight of the load
  • Failing to consider the centre of gravity
  • Using unsuitable lifting accessories
  • Using damaged lifting accessories
  • Ignoring Working Load Limits
  • Failing to consider sling configuration
  • Incorrect machine positioning
  • Poor ground conditions
  • Positioning too close to an excavation
  • Failing to identify underground services
  • Failing to identify overhead services
  • Poor communication
  • Allowing unnecessary people into the lifting area
  • Inadequate exclusion zones
  • Continuing when conditions deteriorate
  • Changing the lifting method without reassessing the operation
  • Reusing an old plan without checking whether conditions have changed

A good lift plan is valuable only when the people carrying out the operation understand it and follow it.

What Happens if Conditions Change During the Lift?

The operation should not simply continue because a lift plan has already been prepared.

Site conditions can change.

Weather may deteriorate. Ground conditions may prove different from those expected. Access can become restricted. Equipment can become unavailable. The load may differ from the information originally provided.

If a change affects the safety or validity of the planned lifting operation, the operation should be stopped and reassessed appropriately.

The plan exists to help control the operation.

It should never become a reason to continue with a method that is no longer safe.

IMPORTANT

If the Lift Changes, Reassess the Plan

A lift plan is based on a particular set of conditions. If the load, equipment, configuration, ground conditions, personnel or surrounding hazards change significantly, stop and establish whether the lifting operation remains safe before continuing.

Can You Reuse a Lift Plan?

Potentially, but only where the plan remains appropriate to the lifting operation and current conditions.

This is particularly relevant to repetitive lifting operations.

A suitable plan for a repetitive operation may continue to be applicable where the load, equipment, environment and method remain within the conditions covered by that plan.

However, it should not become a paperwork exercise where yesterday’s document is automatically used today.

The lifting team still needs to confirm that the assumptions and conditions on which the plan is based remain valid.

Lift Plan vs Risk Assessment – What’s the Difference?

A risk assessment and a lift plan are related, but they are not simply two names for the same document.

The risk assessment identifies hazards, evaluates risks and determines the controls needed.

The lift plan sets out how the lifting operation will actually be organised and carried out safely.

For example, a risk assessment might identify overhead power lines as a significant hazard.

The lift plan then needs to reflect how the operation will be positioned, controlled and carried out so that the identified risk is properly managed.

The documents and planning process should work together.

Do You Need Training to Write a Lift Plan?

Competence is the key requirement.

Someone responsible for planning lifting operations needs sufficient knowledge, training and experience for the type and complexity of lifting work involved.

Completing a training course alone does not instantly make somebody competent to plan every type of lift.

Experience, technical understanding and familiarity with the equipment and operations involved are also important.

For people taking responsibility for planning lifting operations, our NPORS Appointed Person Lifting Operations Training provides structured training in lift planning, equipment selection, risk assessment and safe lifting operations.

Lift Planning Training with Vally Plant Training

Developing an effective lift plan requires more than learning how to complete a form.

The person planning the operation needs to understand how the load, lifting equipment, accessories, ground conditions, personnel, communication and surrounding hazards interact.

Vally Plant Training provides training for the different people involved in lifting operations.

Those responsible for planning can undertake NPORS Appointed Person Lifting Operations Training.

Personnel responsible for controlling lifting operations on site can undertake Lift Supervisor and Crane Supervisor Training.

Those responsible for slinging loads and directing operators can undertake NPORS Slinger Signaller Training.

Excavator operators who lift suspended loads can undertake NPORS Excavator as a Crane Training.

Training is available at our Tewkesbury training centre in Gloucestershire and, where suitable for the course, on customer sites throughout the UK.

PRACTICAL LIFTING INSIGHT

A Good Lift Plan Must Work in the Real World

A lift plan is only useful if the lifting team understands it. If the operator, Slinger Signaller or Lift Supervisor is unclear about the load, method, communication or their individual responsibilities, clarify the issue before lifting begins. Once a load is suspended is not the time to discover that different members of the team understood the plan differently.

Related Guides

For a detailed explanation of the legislation governing lifting equipment and operations, read our LOLER Explained Guide.

If you’re unsure about equipment capacities and load-rating terminology, our SWL vs WLL Explained Guide explains Safe Working Load and Working Load Limit.

Where excavators are used to lift suspended loads, our Excavator as a Crane Safety Guide explains the additional hazards, machine requirements and lifting considerations involved.

LIFT PLANNING QUESTIONS

Frequently Asked Questions

Straightforward answers about lift plans, competent persons, LOLER, BS 7121 and planning safe lifting operations.

What is a lift plan?
A lift plan explains how a lifting operation will be organised and carried out safely. Depending on the operation, it can cover the load, lifting equipment, accessories, capacities, site conditions, hazards, personnel, communication arrangements and lifting sequence.
Does every lifting operation need a lift plan?
Every lifting operation involving lifting equipment at work must be properly planned by a competent person. The amount of planning and documentation should be proportionate to the complexity and risks of the operation.
Who is responsible for preparing a lift plan?
The operation must be planned by a competent person with appropriate knowledge and experience. For crane lifting operations, the planning role is commonly associated with the Appointed Person.
Is a lift plan a legal requirement under LOLER?
LOLER requires lifting operations involving lifting equipment to be properly planned by a competent person, appropriately supervised and carried out safely. The level of documentation should be suitable for the operation and its risks.
What should be included in a lift plan?
Depending on the lift, the plan may need to cover the load and its weight, centre of gravity, lifting points, equipment and configuration, lifting accessories, capacities, ground conditions, hazards, exclusion zones, personnel, communication arrangements and lifting sequence.
What is BS 7121?
BS 7121 is a series of British Standards providing recognised guidance for the safe use of cranes. It covers areas including planning, competence, supervision, equipment selection and the organisation of crane operations.
Can you reuse the same lift plan?
A plan may be suitable for repetitive lifting operations where the relevant conditions remain within those covered by the plan. It should not simply be reused without confirming that the load, equipment, configuration, ground conditions and surrounding hazards remain suitable.
Can an excavator be included in a lift plan?
Yes. Where a suitable excavator is used for suspended-load lifting, the operation should be properly planned. Factors can include machine lifting capacity, configuration, approved lifting point, load weight, operating radius, ground conditions, lifting accessories and manufacturer information.
What is the difference between an Appointed Person and a Lift Supervisor?
The Appointed Person is associated with planning and organising the lifting operation. The Lift Supervisor supervises the operation on site and helps ensure it is carried out in accordance with the agreed plan.
What training do I need to plan lifting operations?
People responsible for planning lifting operations need sufficient competence for the work involved. Vally Plant Training provides NPORS Appointed Person Lifting Operations Training for candidates who need to develop their knowledge of lift planning, equipment selection, risk assessment and lifting operations.

Need Training for Your Lifting Team?

A safe lifting operation depends on competent people understanding both the plan and their individual responsibilities.

Vally Plant Training provides NPORS Appointed Person Lifting Operations Training for those responsible for planning lifts, Lift Supervisor and Crane Supervisor Training for those supervising the operation, NPORS Slinger Signaller Training for personnel attaching and controlling loads, and NPORS Excavator as a Crane Training for excavator operators involved in suspended-load lifting.

Training is available at our Tewkesbury, Gloucestershire training centre and on suitable customer sites throughout the UK.

LIFTING OPERATIONS TRAINING

Plan It. Brief It. Lift It Safely.

From planning and supervision to slinging loads and operating lifting equipment, Vally Plant Training provides practical NPORS lifting operations training for individuals and employers.

View Appointed Person Training

NPORS Plant Operator Training Courses

Visit our Courses page to see our list of popular courses offered at our training centre in Tewkesbury, Gloucestershire or on-site throughout England.

Scroll to Top